Rollover Pass Pier Opening in Gilchrist: What Still Needs Work

When will the pier at Rollover Pass open? Anyone driving Highway 87 through Gilchrist this fall has seen the long T-head out over the Gulf and wondered whether it's already done. For the most part, it is. The concrete deck, the railings and the lights are all in place. The work left is mostly on land: a parking area, a park across the highway, and the price the county plans to charge. That land-side work is what sets the calendar now.

The Date Has Already Moved Twice

This project has outlived several target dates. Here is the sequence, with each date given by the source that reported it:

  1. March 2024. The original construction contract was signed, according to a Texas General Land Office spokesperson quoted by Chron.
  2. July 2024. Hurricane Beryl caused what the GLO called "widespread damage and a work delay" at the site.
  3. Mid-March 2025. Construction began. The GLO's announcement said the work would take about 15 months, with completion estimated for July 2026.
  4. July 30, 2026. Chron reported that the contract had been extended to December 24, 2026. The GLO had also added five days to "investigate the need for buried infrastructure removals." Completion before year-end was still expected, "barring any other delays that may occur that are beyond the GLO and contractor's control."
  5. September 4, 2026. In a Bolivar Live update from the Bolivar Peninsula Tourism and Visitors Center, host David said he expected the opening to come after the first of the year, "probably January maybe 1st or February." He said he hoped it would be open by spring break 2027.
  6. October 18, 2026. In Bolivar Live's fall update, the same host said he hoped for a March opening in time for spring break. He also said, "Don't know if that'll be the case."

The December 24 contract date comes from the state. The winter and spring dates are one well-connected local observer's hopes, and he labeled them that way. The sequence also shows the guesses moving later as the work moves off the pier and onto the ground around it.

Out on the Water, the Pier Is Close to Finished

The October video opens with the host saying the pier is "on the downhill leg being completed." The aerial footage shows a structure that already looks like a fishing pier. Here is what the official plans and the two Bolivar Live visits describe:

  • Length and shape. A 1,000-foot, T-shaped pier extending into the Gulf, described by the GLO as lighted and accessible.
  • Rod holders. The host said he was told there are 140 of them.
  • Cleaning tables. Two tables that appeared to be stainless steel, each with an inlaid cutting board. He said the pier will have water service but wasn't sure about electricity.
  • Lighting. Walkway lights on both sides, aimed so they don't shine in anglers' eyes, plus fixtures pointed down at the water that he expects to help with night fishing.
  • How it's built. Through-bolted railings and a concrete deck with expansion joints, which the host said are built to stand up to storms.

In September, the host said the water off the T-head is deep enough for sharks and trout in summer and black drum in winter. The navigation lights now on the end of the pier are temporary and will be removed.

The pilings from the temporary cofferdam are also starting to come out. The October video shows sand that had built up on the east side of the cofferdam spreading back out, so that stretch of beach is returning to its normal shape.

The Work Left Is Parking, a Park and a Price

The same October update makes clear the project is not finished: "there's a lot of work in the parking area and the park area." That work happens in two places.

On the Gulf side, the plans call for a visitor parking lot and a dune walkover. The GLO also lists a bait shop. Chron's July coverage describes a beach split into an umbrella-rental section and a camping section, with vendor stands and a fish-cleaning station nearby. In October, the host said he had been told the building would "start taking shape" the following week.

Across Highway 87, Bayside Park is still dirt and concrete. The October footage shows a bridge for vehicles, with parking likely in the center, and concrete footbridges built to vehicle standards. Crews are trucking in fill on the north side because the soil there washed away in Hurricane Beryl. Plans call for hiking trails, a birdwatching tower and a kayak-rental kiosk for paddling East Bay. The host described an observation deck with views across Rollover Bay and of the barge and ship traffic on the Intracoastal Waterway. He also mentioned work on the islands behind Rollover. A January 2025 Chron report listed restrooms and showers in the plans as well.

Then there's the price. In the September video, the host said Galveston County "are going to charge some on it." He said county staff were working out pricing when he asked, and that readers had raised questions about entry fees, parking and access from the beach. The county's paperwork on the site so far has been about infrastructure. On September 15, 2025, Commissioners Court approved a utility easement with the Bolivar Peninsula Special Utility District for a waterline to the Rollover Pier project.

A pier with nowhere to park and no posted rules isn't ready to open. Those three pieces of work are what will set the opening date.

What a $31.6 Million Project Brings to This Stretch of Highway 87

Chron reported in March 2025 that the project would cost $31.6 million, split "virtually 50/50" between state and federal money. The federal share included $12 million in community-development block grant funds and $3.3 million from FEMA. Most of the state's share came from the Surface Damage Account. The GLO's federal grant report for the second quarter of 2026 describes the pier as a replacement for a pier lost at San Luis Pass in Hurricane Ike.

The pier is part of a larger package. Texas Land Commissioner Dawn Buckingham described the project as covering the pier, Bayside Park and restoration of the Lauderdale Boat Ramp and Dock. She said it would "strengthen vital habitats" and expand recreation on the coast. Galveston County is the GLO's local partner on the project, which the state lists as a shoreline-access project under its CEPRA coastal program.

The businesses nearby have been waiting through the construction. Miss Nancy's Bait Camp, at 1842 State Highway 87, sits within sight of the new pier. Its owner told Chron this summer that the construction hadn't hurt business and that she was looking forward to the opening because "there will be plenty of business to share." In September, the Bolivar Live host said that Gilchrist "sort of slowed down" and that some businesses closed after Rollover Pass closed. He predicted the pier would help bring the area back over the next couple of years.

The new pier also comes with a lingering local argument. Chron noted that closing the old pass still upsets some residents, and that critics questioned spending on a pier ahead of other infrastructure. The Bolivar Live host's view in October was that the pass "was closed. There's nothing we can do for it," and that the peninsula is getting a pier like the ones in Galveston and Corpus Christi.

Watching It From Home Between Now and Opening Day

Bolivar Live keeps a Rollover Pier camera on its live webcam page, so you can check progress without driving out. The channel plans more aerial updates as the parking and park areas come along. The next fixed date is December 24, 2026, when the extended state contract runs out. After that, opening day depends on the county finishing the parking and park areas and setting its prices.

If you own near Rollover or have been thinking about what the pier means for the east end of the peninsula, I'm glad to talk through what I'm seeing along Highway 87 as the opening gets closer. Let's connect. You can reach me through Norma Smalley.

Work With Norma

With nearly 20 years of experience and deep local knowledge, Norma offers thoughtful guidance, strong advocacy, and personalized service tailored to your needs. From first conversation to closing day, you’ll have a dedicated professional focused on making your experience smooth, informed, and successful.

Follow Me on Instagram