Cranes at the Bolivar Ferry Landings: What's Being Rebuilt, and What Riders Will Notice Through 2029

"Two landings in Bolivar and two landings in Galveston must remain operational at all times." That line is in the general notes of a TxDOT construction contract for the ferry landings, where work began in May 2026 and crane crews operate beside the boats.

Each terminal has three slips, so that sentence describes a ferry that works with one berth out of service on each side while the rebuild is underway. For anyone who crosses between Port Bolivar and Galveston every week, that rule will shape the next few years of the ride more than the new boat TxDOT has announced.

Two Contracts, One Builder, Six Slips

The work at the landings is two separate state contracts running side by side. Texas Gulf Construction Company, Inc. holds both.

Ferry Landing and Facilities Upgrade Ferry Ramp Repair
Contract 12253001, CSJ 0367-06-065 03264004, CSJ 6476-75-001
Award amount $53,235,450 $40,819,142
Awarded December 16, 2025 March 25, 2026
Work began June 9, 2026 May 18, 2026
Scope Landing and slip replacement, dolphins, shoreline, roadway and utilities Ramp refurbishment, hoists, fenders and dolphins, transfer spans, walkways, security booths, shore power

The bigger job is the one the state registered with the Texas Department of Licensing and Regulation as the Galveston and Bolivar Ferry Landings Improvements. That registration estimated the project at $57.7 million. It covers replacing landings and slips, breasting and guide dolphins, shoreline stabilization, roadway and utility work, traffic and pedestrian controls, and an expansion of the maintenance building on the Galveston side. It lists March 7, 2029 as the completion date. The contract was later awarded for a little over $53.2 million.

The second contract repairs the machinery a car rolls over at both terminals, from the Galveston Landing to the Bolivar Landing. The Texas Transportation Commission approved it at its March 25, 2026 meeting. The ramp-repair documents refer to the landings program by its project number. They also treat it as a concurrent job whose construction limits which slips are available.

Together, the two awards put more than $94 million into the two landings. That's before the state spends anything on a new vessel.

The Rule Riders Feel Is the Slip Count

The ramp-repair contract spells out how the crews have to work around the boats:

Once construction is underway on the Ferry Landings Improvements program (CSJ 0367-06-065), only two slips at each ferry landing site will be operational at any given time. The removal and replacement of guide dolphin floating donut fender systems will be allowed between the hours of 8:00 p.m. and 6:00 a.m. at any of the six landing slips.

Other parts of the same document matter just as much. Ferry vessels "will not use the landing in which work is being performed unless an unforeseen emergency should arise." No lifting is allowed while a vessel is maneuvering in that landing or the one beside it. Crane crews have to talk with vessel operations, and "Vessel operation shall take priority." The contractor also has to clear equipment out of the ferry landing or work dock over weekends unless it gets approval.

The landings-upgrade contract has the same rule: two landings on each side stay open, and no boat uses a landing that is being worked on. It also requires at least seven days' notice to TxDOT's Houston District Public Information Office before any "total closure." The ramp contract requires a detailed work sequence, approved by TxDOT, before mobilization. It also requires lane and landing closures to be coordinated with nearby projects so the public is affected as little as possible. That sequence hasn't been published. Neither has a calendar showing which slip goes offline when.

Put the slip count next to TxDOT's own description of the service. On the Galveston–Port Bolivar ferry page, the department says one vessel runs around the clock, a second goes into service at 6:30 a.m., and more are added as demand requires. Up to five can run during summer and holiday traffic. The same page warns that high-season waits can run past two hours. It also says how many vessels are available depends partly on shipyard and maintenance schedules. The fleet sets how many boats can be on the water. The construction rules set how many berths are open at each end of the crossing, and for the length of the program that number is two per side.

Where Each Job Stands as of the October Report

TxDOT publishes contractor estimate reports for active jobs. The latest for both contracts is dated October 8, 2026, and covers work through September. The two jobs are moving at very different speeds.

The landings upgrade estimate shows the job 20.11% complete with 6.01% of contract time used. About $10.75 million had been earned by the end of September, and $3.19 million of that came in September alone. The projected contract amount has crept up to $53,465,450.

The ramp repair estimate is the opposite. As of the same report, 18.63% of the contract time was used, the job showed 0.00% complete, and no item earnings had been recorded through September. The contract runs 730 bid days from its May 18 start. The contract does allow some repair and maintenance to be done on the contractor's own property, with 24 hours' notice so an inspector can attend. Not every piece of this job has to happen at the waterline.

So most of the earned progress so far belongs to the landings upgrade, the job that rebuilds slips and dolphins. The ramp work, which covers hoists, transfer spans, walkways and security booths, has billed almost nothing so far and has most of its schedule ahead of it. Both run on the same few acres of shoreline at each terminal, and both answer to the same two-slip rule.

The Boat Comes at the End of the Rebuild

TxDOT and the Texas Transportation Commission announced on June 24, 2026 that the next vessel for the Galveston–Port Bolivar run will be named the "J. Bruce Bugg, Jr." It honors the commission chairman who served for 10 years, eight of them as chairman. The release says it will carry nearly 500 passengers and 70 cars per trip, plus six crew, with a salon deck and observation decks. The commission awarded the $79,906,625 build contract to Thoma-Sea Marine Constructors, LLC.

The last addition to the fleet was the Esperanza "Hope" Andrade, built in 2023 by Gulf Island Shipyard and dedicated in March 2024. The Bugg is expected to launch in 2029, the same year the landings registration lists for completion. The program's dates line up this way:

  1. December 2025: landings upgrade awarded.
  2. March 2026: ramp repair awarded.
  3. May and June 2026: ramp repair work begins May 18, and landings work begins June 9.
  4. June 2026: the J. Bruce Bugg, Jr. build contract is approved.
  5. 2029: expected vessel launch, and a registered landings completion date of March 7.

The new slips and the new boat are timed to finish around the same point. The years before that are the stretch where the ferry runs on rebuilt ramps, rotating slip closures and the current fleet.

What to Check Before Heading to the Landing

No TxDOT advisory has yet announced closure dates or service changes tied to this work. The contract does promise a seven-day notice to the Houston District before any total closure, so the tools TxDOT already points riders to are the best way to keep up:

  • Wait times: Houston TranStar's ferry wait-time page puts a low-demand trip from the Seawall to Bolivar, or the reverse, at about 45 minutes. It posts real-time estimates when they're available.
  • Bolivar-side camera: the Bolivar landing feed shows the line at Port Bolivar.
  • Galveston-side camera: the Galveston landing feed covers the trip home.
  • Ferry information line: 409-795-2230. TxDOT notes that severe weather can reduce or stop service on its own, apart from any construction.

The contract estimate reports linked above are public and update with each billing period. They're the most direct way to see how far along the slip and ramp work is between now and 2029.

When a showing, an inspection, a closing or a move-in depends on getting across the water, the ferry schedule becomes part of the plan. Norma Smalley is based in Crystal Beach and can help plan peninsula appointments around the crossing for buyers and sellers coming from either side of the bay. If you have a Bolivar Peninsula move coming up, Let's Connect.

Work With Norma

With nearly 20 years of experience and deep local knowledge, Norma offers thoughtful guidance, strong advocacy, and personalized service tailored to your needs. From first conversation to closing day, you’ll have a dedicated professional focused on making your experience smooth, informed, and successful.